Approach and methodology
The project planning was relatively straightforward, given that both towers were located next to one another and overseen by the same project team. An on-site induction was conducted to confirm that all personnel were adequately prepared to work safely.
Initially, we deployed one fire door surveyor and one fire stopping surveyor to evaluate the foot traffic on site before determining the need for additional resources.
Our highly experienced Site Supervisor ensured there was a seamless surveying process and effectively managed the Checkmate Fire team on location.
It was imperative that the team signed in and out at the reception daily and we provided the client with regular updates that included, but were not limited to, progress made, access challenge, and common defects identified on site.
Considerations
On-site, it was imperative that we did not disrupt the other contractors engaged in high-priority tasks. Each morning, we coordinated and resolved any potential conflicts with them to create a collaborative working environment and prevent any complications for the client. Given the strict timelines associated with this project, it was crucial that all tasks were completed ‘right first time’, as there was no room for error.
Key challenges
Timescales were the most significant challenge for our team, as it was imperative that we completed our work by Friday, May 16th, two weeks before the building's official completion date, to allow any time needed for any snagging.
The contractors present on site were initially reluctant to collaborate with us, given that we were independently assessing their work. Consequently, it took time to develop a cooperative environment and teamwork, ultimately making the project more manageable and amicable.
Lessons learnt
The primary lesson learnt from this project was the realisation that complete and unrestricted access to the construction site cannot be assumed. We found it necessary to return to the client to clarify why the number of surveyed door samples was lower than initially estimated, attributing this to access limitations on site. The client was receptive and agreed with our findings.
Benefits
We provided an extensive and thorough report that outlined all necessary remedial and replacement actions required on-site, clearly documented in a dashboard format. This enabled the client to quickly identify all the issues and our suggested corresponding solutions.
The client expressed their appreciation to Checkmate Fire and the team engaged in this project, as we offered independent verification and significantly contributed to helping the client tackle the challenges they encountered. We anticipate that this will lead to additional opportunities for collaboration with the client.