Key challenges
We were able to overcome both a lengthy validation process that we were originally unaware of and extended delivery dates from Gerda. Although the client didn’t have R&D information we managed the process through our trusted asbestos partner. Working in central London often presents unique challenges; however, despite the difficulties, we successfully met all CDM requirements.
Although the client was unable to provide any area for welfare facilities, we overcame this by leveraging our relationships with building managers to find available space. Checkmate Fire also adhered to detailed planning from health and safety departments to ensure all legislative and regulations requirements were adhered to.
Lessons learnt
There was a significant duration between the initial client contact and the installation. This delay mainly stemmed from the validation procedure, which involved inspecting and photographing every door in each building, regardless of how many were originally identified in the FRA report.
Following this step, approval had to be obtained from both the client and CA for any additional doors before progressing to measurement surveys. Subsequent delays occurred due to Gerda's surveyor needing to measure all doors individually, further exacerbated by a shutdown during Christmas time.
The delivery of the doors became notably protracted as a result. However, we successfully expedited this process through our strong partnership with Gerda.
Benefits
Although the project has yet to be completed, final costs will be on budget as we are on framework rates, all works will be certified and we have had no accidents.